The assisted living phase II is now going to be seeing permanent power put in to place, and the new resident alarm system is being added. We were hoping to be able to start moving new residents in on June 1st, but this is looking difficult as the final stages are coming in to place. With all the rain that has been happening, we do not have a safe road behind the Villa where residents would drive in.  Hopefully we can get this fixed and ready to go so residents will be able to move in when the Villa is completed.

The courtyard only about a month ago.

Elaine's Garden & Courtyard as of May 20, 2011.

Just a few short months ago.

Cabinetry in place and ready for counter tops.